Illustrative image – not actual.The Karnataka state government is working out a new payment mechanism for Nagarjuna Power Corporation's (NPCL), 1,015 MW power project near Mangalore, as a result of which the project is likely to take off. The project is estimated to cost Rs.4,500 crore.
The new mechanism, which does not entail an escrow cover or a state support agreement, would provide a reforms-based payment security mechanism for the project. The government plans to set aside a separate fund from the disinvestments proceeds which would be activated a month before the project commences.
According to reports, this is the first time an infrastructure project has received clearance on the basis of a reforms-based payment security mechanism, which was authored by Crisil Advisory Services.
In its order on the fresh payment mechanism, the government has given several options to the promoters:
· The state government may provide a reforms-based payment security mechanism with letter of credit provision to NPCL, but without escrow cover, a government guarantee or a state support agreement.
· The government may provide a reforms-based security mechanism similar to the one offered to Karnataka Power Corporation's Raichur thermal power station, unit VII, without any guarantee.
· It may also permit NPCL to set up a 1,015 MW thermal power plant in the Udupi district of the state, on its own or allow third-party sale within or outside the state, provided NPCL agrees to pay wheeling charges to the state.
In case NPCL is agreeable to any of these alternatives, the draft power purchase agreement (PPA), between the parties concerned, would be suitably modified to facilitate the signing of the final pact, subject to the acceptance of tariff by Karnataka Power Transmission Corporation (KPTCL), and the Karnataka Electricity Regulatory Commission (KERC).
This new order follows a high court directive to the state government, asking it to consider NPCL's demands and work out a payment mechanism.
It may be
recalled that NPCL had signed the PPA, which included a government guarantee
and an escrow cover for the project, with KPTCL in July, 1999. However, the new
Independent Power Policy (IPP) policy, which was against providing escrow cover
to any power project in the state, came into effect in February, 2000.
Subsequently, NPCL had appealed against the government order.
Many other power projects in Karnataka, that have been denied escrow cover
following the acceptance of the Deepak Parekh committee report, which had
rejected escrow cover for all power projects in Karnataka, by the state
government, are likely to benefit from this new order.