Illustrative image – not actual.The government has issued fresh guidelines aimed at reducing delays in public investment projects and for faster implementation of these projects. This guidelines include:
- Fresh appraisal and approval will be required in case costs increase by Rs.500 crore for a single project, instead of the current practice of Rs.150 crore, for projects being undertaken by the ministry of surface transport.
- The government has permitted ministries to approve increases in costs that may occur on account of exchange rate variations, statutory levies and price escalation during the approved project time cycle. These cost increases may be approved by the ministries independently or in consultation with the Planning Commission. The new rules will be applicable to all projects formulated in the Eleventh Plan period from 2007-12.
- The government departments will not be required to seek fresh approval for getting equity or loan support in the 11th Plan in case these funds are within the already approved limits.
- Any support beyond the approved limit-in the form of the central government or a central public sector enterprise (CPSE) providing share capital to a new or any existing company-will require fresh appraisal/approval.
- The Expenditure Finance Committee (EFC), headed by the expenditure secretary, will 'appraise' all those projects, which involve setting up of new autonomous bodies, central universities or special purpose vehicles, irrespective of the outlay or the nature of ministry or department. All such will need to be approved by the Union Cabinet or the Cabinet Committee on Economic Affairs.