New Ganderbal power project faces hurdlesIllustrative image – not actual.

The new Ganderbal hydropower project, which was cleared after three decades, is facing hurdles as the company has failed to furnish the performance bank guarantee.

Hindustan Construction Corporation was supposed to furnish the guarantee 28 days after the PDC issued the notification to award the contract in its favor in August 2017.

The New Ganderbal hydropower project is coming up at cost of around Rs 1,000 crore.

The project will come up at Sindh river. The Ganderbal project is a run-of-the-river project with three units of 31MW each. The state cabinet cleared the project on 16 June 2017.

Some major work, including construction of access road to the project site and land acquisition, has been completed. This entire work has incurred an investment of around Rs 100 crore.

The project is expected to be completed within 48 months.