Illustrative image – not actual.The EI system of 800 routes was achieved in record time ensuring minimum traffic disruptions or passenger inconvenience.
Preparations for commissioning of this EI system commenced about 18 months back.
The system has integrated two additional platforms at Kharagpur junction, third line from Howrah side and second line from Adra side. Besides, it has ensured operation of down goods departure yard from the main electronic interlocking system at Kharagpur junction.
The EI has been provided in a distributed manner with the interlocking spread over nine zones interconnected with highly reliable optical fibre cables (OFC) in a ring configuration.