Illustrative image – not actual.Karnataka Road Development Corporation (KRDCL) has set December 2026 as the latest deadline to complete the Rs 488 crore Varthur elevated corridor on State Highway-35.
The 100-ft elevated corridor near Bengaluru’s technology corridor, work on which began in May 2019, was originally scheduled for completion by November 2021 but faced repeated delays due to land acquisition, utility shifting, approvals and execution issues. KRDCL Managing Director Susheelamma N and project officials have directed the contractor to expedite pending works and meet the revised year-end target. The agency has completed side-drain works and demolished more than 50 properties between Varthur Kodi and Varthur police station, while 14 properties remain pending for acquisition due to issues involving transferable development rights or cash compensation.
The SH-35 corridor connects Whitefield, Varthur, Gunjur, Sarjapur and Outer Ring Road (ORR), where rapid development has intensified congestion.