Illustrative image – not actual.Karnataka government plans to incorporate a new company, Bangalore Metro, in place of the existing Bangalore Mass Rapid Transit set up for implementing the earlier proposed Elevated light rail transit system for Bangalore.
Centre would contribute Rs.1000 crore and Rs.1,500 crore is to be contributed by the state towards equity. A soft loan of Rs.2338 crore would be provided by Hudco. The tenders for civil works, being prepared by RITES, would be invited by September 2003 and the work is likely to commence from December 2003.
Internal rate of return for the project has been calculated to be 23.4 per cent. The estimated daily ridership for the metro is 8 lakh in 2007. 48.3 hectares of land is required for the project out of which 29.4 hectares is government land and private land is 18.9 hectares.
The cost of the project has been revised to Rs.4989 crore accounting for interest and escalation costs. The state also plans to seek concessions enjoyed by Delhi Metro for the proposed project.