Illustrative image – not actual.On 11 February 2014, a long delayed water supply scheme, 'Netravati river diversion project' in Karnataka, received approval from the state cabinet.
The scheme, being proposed by the National Water Development Agency (NWDA), intends to provide drinking water to Kolar, Chikkaballapur, Tumkur, Ramanagar, and Bangalore (rural districts of the state), by diverting the Netravati river in coastal Karnataka. The project was first taken up in 2011 at a cost of Rs 11,120 crore. Due to delay, the cost has escalated and is now estimated at Rs 12,912 crore. The project will be developed in two phases. Phase-I will cost Rs 3,508.36 crore and Phase-II will entail an investment of Rs 9,404 crore.
The state government plans to re-invite bids soon for the project as it received only one technical bid.