Nerul Jetty to be completed by end of 2021Illustrative image – not actual.
The work on Rs 111 crore jetty in Nerul for water transport from Mandwa to Nerul and Nerul to the Gateway of India in Maharashtra is at the last stage and likely to be completed by end 2021.

The project was hindered due to delay in getting clearance from the Forest Department and later the imposition of the lockdown in 2020.

The water transport is believed to cut travel time by 30 minutes from travelling to Mumbai from Navi Mumbai. At present, by any mode, it takes around 90 minutes to reach south Mumbai from Navi Mumbai.

The work of Rs 111 crore jetty started in 2018 and it supposed to be completed in 24 months. However, it was delayed due to multiple reasons from the delay in getting the Forest Department clearance to the sudden lockdown in 2020.

The project is being developed by the City and Industrial Development Corporation (CIDCO).

After completion of the jetty work, it will be handed over to the Mumbai Maritime Board (MMB) for operation. However, the maintenance of the jetty will remain with CIDCO.

The work on three water terminals, one each at Ferry Wharf, Nerul and Mandwa are already going on. MMB, the nodal agency for the project, has roped in CIDCO and the Mumbai Port Trust (MbPT).

MMB will fund the construction at Mandwa, CIDCO at Nerul and MbPT at Ferry Wharf. All these will be connected to each other.