Illustrative image – not actual.The eighth round of talks, since August 2001, among the partners of Bangalore International Airport Co. Ltd (BIACL) is expected to resume on 18 December 2001.
BIACL is implementing the international airport project in Bangalore. BIACL’s partners are the state government, the Airports Authority of India and the Siemens – Larsen & Toubro – Zurich Airport consortium.
A formal agreement between the partners is expected
to be signed in January 2002, after receiving the necessary clearances from the
state and Central governments. The agreement would relate to the roles and
governance issues of the three partners, project cost and project time.
The project is expected to achieve financial closure
by September 2002, after which work on the project would start in October 2002.
The project is proposed to be completed by January 2005 and start commercial operations
by April 2005.
The project cost as approved by the Centre and state
governments stands at Rs.1,000 crore ($200 million) with a contingency
provision of 7.5 per cent. The state government’s support would be around
Rs.225 – Rs.300 crore ($45 - $60 million) as prescribed by the State Finance
Corporation.