NEEPCO's Tuirial project may be revivedIllustrative image – not actual.

The Union Ministry of Power is mulling to revive North Eastern Electric Power Corporation's (NEEPCO) 60 MW Turial hydro electric project in Aizawl district of Mizoram.

Work has been held up at the project since June 2004 due to public agitation over crop compensation and also because of serious time and cost overruns. The estimated cost of the project has already shot up from Rs 368 crore to Rs 836.14 crore.

In this direction, NEEPCO has provided an investment proposal note for the Public Investment Board, which contains the following two options for reviving the project:

Option-I- A fresh loan of Rs 588.52 crore from Japan Bank for International Cooperation and a Rs 130 crore of subordinate loan from the Union Government
Option-II-A domestic loan of Rs 234.73 crore and a subordinate loan of Rs 480.96 from the Union Government.

← All latest storiesBack to top →