Necessary clearances in place for Versova bridge projectIllustrative image – not actual.

The National Highways Authority of India (NHAI) has received all required environmental approvals for Versova Bridge (also known as the Bhayandar Creek Bridge) project on the Mumbai-Ahmedabad National Highway.

With this, work on the four-lane Versova creek bridge at Ghodbunder junction has picked up pace. The bridge will be completed in two years.

The new bridge will replace 49-year-old two-lane Gujarat-bound bridge that operates at a 20 km per hour speed restriction since rehabilitation. The motorists use a parallel two-lane bridge built in 2000.

The new 918 mtr bridge will be developed at a cost of Rs 157 crore.

The foundation stone for the bridge was laid in January 2018. However, work in many parts, especially, the periphery of the creek, was delayed in obtaining environmental clearances for construction.

On 29 April 2019, NHAI obtained clearance from the Ministry of Environment, Forest and Climate Change (MoEF&CC) for construction in the CRZ. The Bombay High Court granted permission to cut down around 0.6 ha of mangroves in Sasunavghar and Versova in May 2019.

The state forest department and Maharashtra coastal zone management authority had given no-objection certificates for undertaking the project.

Of the total cost, around Rs 18 crore has already been spent on erecting some pillars for the bridge.

 