NDPHC to complete 2,000 MW power stations in Abia, Imo, BayelsaIllustrative image – not actual.
The Niger Delta Power Holding Company (NDPHC) will expedite work on four power plants located in Alaoji, Egbema, Omoku and Gbarain with a combined capacity of about 2,000 MW of power to boost national supply. The company is jointly owned by the federal, state and local governments.

Some of the projects were delayed due to cancellation of contracts by NDPHC to the contractor that was handling it. The company is making efforts to engage new engineering, procurement and construction (EPC) contractors to complete the plants and make them available to the national grid.

In Egbema, Imo State, NDPHC had just taken back the project from its EPC contractors after a long period of delay.

At the 252 MW power plant in Gbarain, Bayelsa State, the company's in-house generation project team was working to ensure that the remaining unit plant comes on stream by 2021.

The Egbema Power plant is a three gas-fired plant units designed to output 378.3 MW ISO to the national grid. This contract was initially awarded in 2006 to Rockson Engineering Company. The contract could not be executed to its design output. The board of NIPP has directed a termination of that particular contract at the end of 2019.

The four power plants were being built by Rockson Engineering. The one in Egbema, there is a 252 MW power plant in Omoku and then there is another 252 MW plant in Gbarain Obie, Bayelsa State, as well as the 1,074 MW Alaoji power plant.

Alaoji and Gbarain are in operation. Parts of them have been completed by the former contractor and have put them into national grid but are yet to complete them to scope.