Illustrative image – not actual.New Delhi Municipal Council (NDMC) is likely to complete the redevelopment work of the Connaught Place in Delhi by July 2013.
For the purpose, NDMC has appointed the consultant -- Engineers India (EIL). The project was originally expected to be completed by June 2013 but increase in the work resulted in delay. The original cost of the project was Rs 76 crore, but as the scope of work increased, the revised cost of the project escalated to Rs 671 crore.
NDMC has completed surface redevelopment work. Only EIL has to now provide electricity connections to traders and install escalators in subways, which is expected to be completed by mid-July 2013.