Illustrative image – not actual.The National Capital Region Transport Corporation (NCRTC) has signed a power purchase agreement (PPA) for a 110 MW solar power plant.
Estimated at around Rs 450 crore, the project will be developed at Jaulan in Uttar Pradesh to meet nearly 60 percent electricity requirement of the Delhi-Meerut Namo Bharat corridor. The plant will supply electricity through the Uttar Pradesh state grid to NCRTC substations in Uttar Pradesh and Delhi, supporting power distribution across the corridor. Under the agreement, NCRTC will procure electricity at a fixed tariff for 25 years, providing greater predictability in energy costs and reducing reliance on conventional power. Electricity currently accounts for around 30-35 percent of the corridor’s operating cost.
The captive solar project is expected to reduce annual electricity expenditure by approx. 25 percent and cut carbon dioxide emissions by about 1.77 lakh tonne annually.