Illustrative image – not actual.
The National Capital Region Transport Corporation (NCRTC) has launched the first precast segment for the Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS) corridor at P382 between Guldhar and Duhai.
The launching girder which is also known as launching gantry is assembled on piers or pillars on temporary supports. Later on, these are removed before segment lifting.
In order to make viaduct, the various segments lifted are joined together to make viaduct. In the first span of 34 mtr, there will be as many as 12 segments.
To launch, join and complete this span, around six days will be taken and afterwards launcher will move towards Ghaziabad side. At present, the launcher is between Guldhar and Duhai.
The segments of RRTS corridor are being casted at the Vasundhara casting yard. The RRTS viaduct will have a design speed capability of 180 km per hour.
The work is making headway on 17 km long section between Sahibabad and Duhai, which is NCRTC’s priority, and soon superstructures will be visible.
The 82 km long Delhi-Ghaziabad-Meerut RRTS corridor project will have a total of 22 stations. Of these 16 stations will be regional stations, while the rest of the six stations will fall in Meerut.
The 17 km section between Duhai and Sahibabad is likely to be open for passengers by March 2023, while the entire corridor is expected to open by 2025.