Illustrative image – not actual.The National Capital Region Planning Board (NCRPB) has disbursed Rs 200 crore of installments for the Noida-Greater Noida Metro project.
The board had earlier released Rs 930 crore towards the project. In February 2016, NCRPB sanctioned a loan of Rs 1,587 crore to Noida Metro Rail Corporation (NMRC) for the 29.7 km Noida-Greater Noida Metro project, which is estimated to cost Rs 5,533 crore and has now been revised to estimated cost of Rs 5,303 crore. In the FY 2017-18 NCRPB has provided a total loan grant of Rs 550 crore.
In the next FY 2018-19, NCRPB will grant a loan assistance of Rs 457 crore. For the first two installments amounting to Rs 580 crore, the loan will be paid back in 20 years, including a moratorium of five years. From the next installment of Rs 245 crore received in July 2017, the loan will be paid back in 19 years including a moratorium of four years. The loan will be repaid at an interest rate of seven percent in 16 installments.
GNIDA, which shares an equity of 30 percent in the corridor, has given a grant of Rs 90 crore and equity share of Rs 90 crore, and still has to give equity of Rs 201 crore and grant of Rs 69 crore towards the Aqua line.
Meanwhile, the metro project is also awaiting the centre's grant release of Rs 970.62 crore.