Illustrative image – not actual.NCL Industries is headed for a significant capacity increase by end-2006 if the steady progress on its various ongoing projects is any indication. The company is in the midst of three projects spread over Andhra Pradesh and Himachal Pradesh, with a total investment of Rs.67.46 crore.
All the three projects are on track and are scheduled for concurrent completion by December 2006, senior officials of NCL Industries informed ProjectsToday.
The first project involves capacity expansion of the existing cement clinker unit at Huzurnagar in Nalgonda district of Andhra Pradesh. The Rs.23.84 crore project will see capacity doubling to 5.94 lakh tpa. Elaborating on the current status, NCL officials stated that the overall completion rate of the project is well over 50 per cent. More than half of the machinery has arrived on the site and erection is likely to begin in August 2006.
The second project entails setting up of a greenfield 3.15 lakh tpa cement grinding unit at Kondapally in Krishna district. The Rs.22.20 crore project, which is now 40 per cent complete, aims at using the surplus clinker from the aforementioned Huzurnagar expansion project taking place in the adjoining Nalgonda district.
At Himachal Pradesh, NCL is putting up a 50,000 tpa cement wood particle board project at Ponta Sahib in Sirmaur district. Civil works for the Rs.22.20 crore are well underway and erection is scheduled to begin by August 2006. The project is scheduled for completion by December 2006, which is three months ahead of the original schedule of March 2007.