NCC's Andhra Pradesh power project in doldrumsIllustrative image – not actual.

The National Environmental Appellate Authority has cancelled the environmental clearance given to Nagarjuna Construction Company's (NCC) 2,640-MW thermal power plant at Sompeta in Srikakulam in Andhra Pradesh.

The Authority found that the project site was a wetland instead of the claim of the sub-committee of the Expert Appraisal Committee of the MoEF. The agricultural activity around the plant was likely to be affected if the plant was allowed.

NCC has reportedly claimed that it has received all the approvals required for the project and has even tied up coal with Mahanadi coal fields with an option of importing about 30 per cent of the coal required for the project.

NCC requires 1,400 acre for the project and had acquired about 900 acre from the state government while the balance was procured from private owners in Sompeta. Villagers allege the company never disclosed the purpose of the land acquisition and had only told them that it will be used for pisciculture. The project has been facing a lot of opposition from the locals as well.

Also See:

NCC to appoint foreign partner (22- June-10)

Related Links:
Project profile

← All latest storiesBack to top →