NCC achieves financial closure for Nellore coal based power plantIllustrative image – not actual.

NCC has tied up funds for the 1,320 MW greenfield coal based power plant slated to come up in Nellore district of Andhra Pradesh.

The company has raised debt of Rs 5,300 crore from a consortium led by REC, PFC, ICICI and other. The Rs 7,000 crore power plant is being executed through a SPV in a JV with Gayatri Projects. The equity component has also been completed. While NCC will chip in with Rs 350 crore, Gayatri and other sources have closed in with the rest. NCC has roped in Harbin of China for boiler supplies and NCC itself will be the EPC and balance of plant services provider. The Unit I of the project is expected to be commissioned in 39 months and the Unit II in 42 months. All mandatory clearances for the project have been obtained.

Also See:

NCC’s Krishnapatnam power project set to achieve financial closure soon (16-August-11)

Related Links:
Project profile

 