NBCC (India) will expedite work on completion of 19 real estate pending projects of Amrapali Group.
The company has doubled its workforce from 6,000 to 12,000 to expedite the completion. While work on 17 projects is underway, one more was handed over to a construction company recently. The last one is expected to be handed over to a company by the end of October 2020.
Since these 19 projects are in various stages of completion, NBCC (India) will take from nine to 36 months to finish construction. In total, 43,518 flats are left to be handed over to buyers.
The responsibility of constructing Dream Valley Phase-II was handed over to a firm recently. The 19th pending project -- Leisure Valley Verona Heights — is likely to be given to a construction firm on 28 October 2020.
While Dream Valley has 8,302 flats, Verona Heights has 4,964 flats pending. In projects that are partly complete and residents have already occupied flats, work on finishing them will go on simultaneously.
NBCC (India) has already handed over Eden Park and Castle projects. In the 17 ongoing projects, the government company has to roughly complete 30,715 flats.
In the two other projects in which NBCC (India) has now started work or will do so in a month, it has to deliver around 13,000 flats.