Illustrative image – not actual.The Maharashtra Government is likely to kick start the metro project for Navi Mumbai in 2010.
The state government is likely to begin work on the project by December 2010 The Phase I of the project is likely to be between Belapur, Kharghar, Taloja and Pendhar and is estimated to cost Rs 1,694 crore.
City & Industrial Development Corporation (CIDCO) is the nodal agency appointed for the metro project. It has shouldered the responsibility of the viaduct for the elevated rail corridor.
CIDCO is expected to complete the financial bidding for the viaduct, for the Phase I with road length of 10.78 km, by December 2010.
The Phase II with an outlay of Rs 1,400 crore is expected to start in December 2012 and complete by December 2015. The Phase III costing Rs 575-crore is scheduled to start in December 2015 and will complete by 2018.