Navi Mumbai airport project to take off, soonIllustrative image – not actual.

The MoEF issued a notification on 18 May 2009 granting exemption to the second airport for Mumbai, at Navi Mumbai from costal regulatory zone (CRZ) regulations.

The Maharashtra government has set a deadline of March 2010 to complete the bidding process and award the contract, and make the airport partially operational by 2013. CIDCO is the nodal agency for the project.

The preliminary report on the project has been submitted by the consultants and their final report is expected to come by 30 August 2009. While bids for the project are likely to be invited by end-September 2009, the process of inviting financial bids will be completed by mid-February 2010 and by end-March 2010, the contract will be awarded.

The Rs. 10,000 crore airport project is likely to be implemented on BOT basis on 2,000 ha near Panvel.

Also See:

HC relief for Navi Mumbai airport project (05-May-09) 