Illustrative image – not actual.Navayuga
Engineering Company (NEC) and Soma Enterprises have jointly promoted a special
purpose vehicle, ‘NYSE Infrastructure’, to construct a 17 km Nellore bypass
road in Andhra Pradesh. The road is being developed on BOT annuity basis and
will have a concession period of 15 years with bi-annual installment payment mechanism.
The
bypass, on NH-5, is a part of Kolkata-Chennai arm of the golden quadrilateral
and would connect Chennai with Vijayawada. The project is estimated to cost
Rs.157 crore and likely to be completed by October 2004.
The
Nellore bypass project involves construction of two bridges spanning a total
length of 1.89 km over the Pennar river, four road-over-bridges, six canal
crossing bridges and ten bridges over underpasses. The road structures would
cost Rs.74.50 crore, while the bridges and culverts will cost around Rs.82.50
crore.
The
project will have a debt to equity ratio of 2.56:1. The two partners will share
the equity of Rs.47 crore in the ratio of 51:49. Talks have reportedly been
initiated with IDBI and ICICI for lead arranging the debt component of Rs.110
crore.
NEC
is also executing the bridge on river Gowthami between Yanam and Yadurulanka in
East Godavari. Also, the company has been awarded contract for constructing
bridges and culverts on a portion of Kanpur-Bhaunti-Fatehpur road (NH-2).