Illustrative image – not actual.Asian Development Bank has begun appraisal for the second round of funding worth Rs.800 crore for six project segments under the National Rail Vikas Yojana.
The six segments in question are:
- Aligarh-Ghaziabad section (third line)
- Khurda Road-Barang section (third line)
- Attipattu-Korrkupat section (third line)
- Tiruvallur-Arrakonam section (third line)
- Rajatgarh-Barang section (doubling)
- Cuttack-Barang section (doubling)
ADB has already approved funding worth Rs.700 crore for four projects; the details of which are as follows:
- Gotty-Pullampet section, doubling (Rs.305 crore)
- Keonjhar-Tomaka section, third line (Rs.170 crore)
- Bhatapara-Urukura section, third line (Rs.140 crore)
- Second bridge over Mahanadi River (Rs.85 crore)
If the Rs.800 crore of the second round comes through, ADB will have exhausted its committment of Rs.1,500 crore ($300 million) towards the National Rail Vikas Yojana, which has a total cost of Rs.15,000 crore.