National optic fibre network to be delayed further Illustrative image – not actual.

The national optic fibre network (NOFN) project of Bharat Broadband Network (BBNL) will face further delay as the cable laying & trenching (C&T) tenders have not yet been finalised.

 

State-run BSNL, PowerGrid and RailTel have been mandated to handle cable laying and trenching responsibilities in the 70:15:15 ratios respectively, and the final value of the contracts will be over Rs 11,000 crore.

 

The project has been delayed for two years, following which the Department of Telecommunications recently sought the approval of the Cabinet Committee on Infrastructure (CCI) to implement the pan-India broadband rollout in three phases, starting with high-speed broadband links in one lakh gram panchayats (GPs) at an investment of over Rs 11,000 crore, by March 2014.

 

Even if the companies award the C&T contract by the end of January 2014, the project is able to achieve a tenth of the broadband coverage target in Phase-I.