National Highway Development Programme: StatusIllustrative image – not actual.

Till September 30, of the total length of 5,851 kms on the Golden Quadrilateral connecting the four metros of New Delhi, Kolkata, Chennai and Mumbai, four-laning has been completed on 978 kms while work on another 3,710 kms was on. NHAI has approved award of contracts for about 93 kms of Golden Quadrilateral and the remaining 1,070 kms would be finalised for award of civil works this year.

 

In case of the North-South and East-West corridor, measuring a total length of 7,300 kms, work has been completed on 675 km, while that on another 739 kms is under implementation. During 2001-02, about 62 kms will be awarded for civil work while the balance 5,824 kms will be taken up in National Highway Development Programme (NHDP) Phase II, which will start from April 1, 2002.

 

Of a total 381 kms of highways connecting the major ports, 74 kms is under implementation while contract for the remaining 307 kms will be awarded during 2001-02.

 

Meanwhile, according to the estimates worked out by the Government, the highways sector will require around 100 lakh tonnes of cement and 8.6 lakh tonnes of steel for the first phase of the NHDP, comprising the entire Golden Quadrilateral, port connectivity and some other stretches.

 

Lakh tns

2001-02

2002-03

2003-04

Cement

27

38

34

Steel

2.5

3.1

3

 

Similarly, in the equipment sector it is estimated that around 5,100 tipplers, 1,020 tractors, 170 excavators, 140 graders (50 per cent domestic), 280 rollers (50 per cent domestic), 35 small batching plants, 100 transit mixers and DG sets (Rs 3 crore for each large package) would be required for the entire NHDP.