NTPC suffered a temporary setback when the National Green Tribunal south zone bench in Chennai, Tamil Nadu, kept the environment clearance (EC) issued to NTPC for its new thermal power plant in Ramagundam in abeyance for seven months.
The NGT bench wanted a re-appraisal done as per the additional terms and conditions of the Union Ministry of Environment and Forest.
NTPC had initially applied for two x 600 MW thermal power plants and later enhanced it to two x 800 MW capacity in violation of the terms.
NTPC was also directed to conduct a fresh study regarding the area for installation of flue gas desulferisation system (a set of technologies used to remove sulfur dioxide) and do a hydro-geological impact assessment on account of the ash pond due to storage of ash slurry, besides study the impact on water quality.
The project proponent should be directed to conduct radio activity and heavy metal test of coal to be used. These tests should also be done for alternative coal and mitigative measures to be taken to reduce impact on environment.
NTPC was told to conduct a cumulative impact assessment of ambient air quality modelling for a radius of 15 km from the project area.