National Green Tribunal cancels environment nod to NCC Sompeta power projectIllustrative image – not actual.

The National Green Tribunal, on 23 May 2012, called off the environmental clearances given to NCC’s coal based power project at Sompeta in Srikakulam district of Andhra Pradesh.

The company was planning to set up a 2,640 MW coal based power project with an investment of Rs 14,000 crore. The project to be implemented in phased manner was to have two phases of 1,320 MW each. The villagers in Sompeta are protesting against the unit. The tribunal has asked the company to go through a fresh round of public hearing for setting up of the project. 
 
Earlier in 2010, police action including several rounds of firing at Sompeta during the protests had resulted in the death of two villagers forcing the company to put the project on hold.
 
As an alternate to the Sompeta project, NCC has been working on the power project at Krishnapatnam after taking over a 1,320 MW project from the Nelcast. In the project, Gayatri Projects holds 45 per cent stake. The project is yet to achieve financial closure.
 
Related Links:
Project profile
← All latest storiesBack to top →