Illustrative image – not actual.Gail (India) on 8 September 2006 stated that around 20 per cent of the National Gas Grid project stood complete, but a timeframe for full completion could not be offered since it hinges on gas availability.
Gail has so far spend Rs.5,500 crore in laying the Dahej-Uran and Uran-Dabhol pipelines, among others. Work on major stretches would be taken up after gas is made available.
The National Gas Grid involves the laying around 8,500 km cross-country pipelines with a total investment of around Rs.18,000 crore. During 2006-07, Gail would spend Rs.3,300 crore on laying a pipeline network of 1,500 km. During the XI Plan period (2007-08 to 2011-12), Gail would invest Rs.12,000 crore on pipeline projects.