Illustrative image – not actual.The Minister of State for Railways, R Velu, on 11 November 2008, inaugurated the Nanjangud-Chamarajanagar broadgauge line, connecting Chamarajanagar railway terminus in the Mysore region on the Karnataka boundary with broadgauge railway line.
The approximate cost of the work on the 36 km stretch between Nanjangud and Chamarajangar is Rs.116 crore, which has 66 minor bridges and two major bridges.
In June 2008, the stretch between Mysore and Nanjangud on the Mysore-Chamarajanagar section was thrown open for traffic following the gauge conversion work. The project was completed at a cost of Rs.197 crore. The Mysore-Chamarajanagar gauge conversion work (61 km) received approval and budgetary sanction in 1997-98 and the project cost was pegged at Rs.85 crore. However, the project cost escalated to Rs.197 crore on account of delay in the implementation of work for various reasons, including construction of two major bridges on the Kabini.
.