National Aluminium Company (Nalco) has announced the
completion dates for its on-going Orissa projects, viz. the mine and mineral
complex and the smelter project.
The company has stated that the completion of the third
stream of its Damanjodi mine and mineral complex in Orissa will be completed by
15 July 2001 and production would commence by October 2001. The refinery
project entails an investment of Rs.1,600 crore.
The company’s smelter project and captive power plant
at Angul in Orissa, were scheduled for completion by May 2002. This smelter
project involves an investment of Rs.2,400 crore.
The company also stated that the 100 per cent export
oriented unit of its subsidiary, International Aluminium Products Ltd, was
scheduled for completion in July/August 2001. Commercial production from this
unit was expected to start in October 2001. This project entails an investment
of Rs.350 crore and would have a capacity to produce 50,000 tonnes of
value-added products such as aluminium sheets of various thickness.