NALCO is expected to complete capacity expansion and commission its 5.25 lakh tpa refinery at Damanjodi in Koraput district of Orissa soon.

Work on the last leg of the refinery's sixth stream is expected to be over soon. In the first two months after commissioning, the capacity utilisation will be around 80 per cent and by June 2011, 100 per cent capacity utilisation is slated to be achieved.

Meanwhile, the expansion project of NALCO, including a 240 MW power unit and additional smelting capacity will be also be over with the commissioning of the refinery.