Illustrative image – not actual.National Aluminium Co Ltd (Nalco) is
hopeful of getting Public Investment Board (PIB) approval for its Phase II expansion
project by October 2003. All clearances are expected to be in place by end of
2003-04.
In the second phase costing Rs.3,500
crore, significant increase is envisaged in the mining, refining and smelting
operations. Besides, captive power generation capacity would also be enhanced
to support the expanded capacities.
After the PIB approval, which was
sought in May 2003, comes through, the proposal would be forwarded to the
Cabinet Committee on Economic Affairs for further clearance. The final approval
is expected to come by March 2004. The expansion project has already received
clearance from the ministry of mines, finance and programme implementation, and
the Planning Commission.
The project has a gestation period
of around four years, and would be financed through internal accruals. The project
envisages the following enhancements in capacity:
Nalco
Expansion: Phase II
|
|||
|
Facility |
Capacity
|
||
|
Unit |
From* |
To |
|
|
Bauxite
Mining |
million
tpa |
4.8 |
6.3 |
|
Alumina
Refining |
lakh
tpa |
15.75 |
21.00 |
|
Aluminium
Smelting |
lakh
tpa |
3.45 |
4.60 |
|
Captive
Power |
MW |
960 |
1,200 |
|
*After
completion of ongoing Phase I |
|||