Illustrative image – not actual.National Aluminium Co has invited global pre-qualification bids for its captive power plant expansion project. Nalco is expanding its existing 960 MW power plant (comprising eight units of 120 MW) each, by setting up two more units of 120 MW, taking the total capacity to 1,200 MW.
The scope of work includes design, manufacture, supply, erection, testing and commissioning of main power house comprising:
- boilers & auxiliaries
- turbo generators & auxiliaries
- field instruments
- civil and structural works of main power house package
The envisioned gestation period is 26 months, and the last date of submission of bids is 2 July 2004. For more details, please contact:
General Manager (P&T)
National Aluminium Co Ltd
Nalco Bhavan
P/1, Nayapalli
Bhubaneshwar 751 013
The project forms part of Nalco's Rs.4,000 crore integrated project (Phase II) wherein the following capacity expansion is envisaged:
| Facility | Unit |
Capacity Expansion |
||
| By | From | To | ||
| Bauxite Mining | mln tpa | 1.5 | 4.8 | 6.3 |
| Alumina Refining | lakh tpa | 5.25 | 15.75 | 21.00 |
| Aluminium Smelting | lakh tpa | 1.15 | 3.45 | 4.60 |
| Captive Power | MW | 240 | 960 | 1200 |
The project has received approval from the Public Investment Board in February 2004.