Nalco commissions captive power plant at AngulIllustrative image – not actual.

The National Aluminium Company (Nalco), commissioned the seventh 120 MW unit of its captive power plant at Angul (Orissa) on 2 December, 2002. The seventh unit, erected at a cost of Rs. 420 crore, incorporates advance features in pollution control.

 

Nalco, under an expansion plan to increase captive power generation capacity to 960 MW, is adding two more units of 120 MW.  The company, which already has in its fold, six generating units of 120 MW capacity totalling 720 MW, required the matching expansion of the captive power generation capacity to raise its smelter capacity from 2,30,000 tonnes to 3,45,000 tonnes.

 

Construction of the eighth 120 MW unit is expected to be completed by the first quarter of 2004.

 

 

 