Illustrative image – not actual.NALCO's proposed aluminium project in Orissa is likely to be delayed. The company is yet to receive the environment clearance from the state government. Also, a report from Nagpur based National Environment Engineering Research Institute is awaited.
The company plans to set up a five lakh tpa aluminium smelter and 1,250 MW power plant at Brajrajnagar in Orissa near its existing aluminium smelter. The proposed project is estimated to cost Rs 10,000 crore. NALCO intends to start construction for the proposed project in 2012 and commission it by 2017.
This apart, the company is ramping up its existing facilities at an investment of about Rs 4,400 crore. The proposed expansion is being funded through internal accruals.
As part of the plans, the company has already expanded the capacity of aluminium smelter from 3.45 to 4.6 lakh tpa at Jharsuguda. The smelter has commenced the commercial production. Further, the capacity of its captive power plant has been raised from 960 to 1,200 MW and it has begun power generation.
However, the company is facing delay in launching the expanded 2.1 million tpa alumina refinery at Damanjodi. Presently, the refinery has a production capacity of 1.57 million tpa. The refinery is likely to be delayed in January 2011.