Nairobi to complete road upgradation project by 2022-endIllustrative image – not actual.
The Kenya Urban Roads Authority (Kura), a state corporation under the Ministry of Transport and Infrastructure, recently announced that it is on course to complete the over USD 48.89 million Nairobi informal settlements road upgrade project by December 2022.

The project, which was launched in November 2020, involves re-carpeting and upgrading a total of 408.4km of roads into cabro and asphalt (bitumen) standards, in addition to the installation of additional road infrastructures such as walkways and cycle lanes where there is adequate space.

Out of the 408.4 km, 152.7 km have already been completed including the 57.4 km or its thereabouts completed between the launch of the project and June 2021 , and the approximately 95.3 km completed in only three months between June and August 2021.

The project will benefit more than 12 informal settlements in Nairobi. According to the overall plan, a total of 70 km will be upgraded in Mukuru slums, 57.48 km in Githurai, 50.76 km in Roysambu, another 42 km in Mwiki, 41 km in Kangemi, and 40 km in Dandora, Utawala, Mihang’o, and Ruai.

In Dagoretti, Kawangware, Kibera, Mathare, and Korogocho approximately 30 km, 22.6 km, 22.8 km, 18.2 km, and 13.6 km of road will be upgraded respectively as part of the project.