The Nagpur Municipal Corporation (NMC) expects construction of Metro Mall to be completed in 30 months.
NMC’s project department has submitted a proposal in this regard before the standing committee which will meet on 10 November 2021. Recently, it had shortlisted a private agency which has agreed to pay Rs10 crore more than the bid amount of Rs 45 crore.
NMC had floated tenders to build eight floors comprising shopping mall, restaurant and multiplex with rooftop eatery. The mall, which was Phase-I Scheme of the Orange City Street project, will be a public private partnership project.
The civic body had floated tenders in October 2019. A base price of Rs 45 crore was fixed for 35,000 sq mtr land where the mall will come up. NMC had finalized Praful Ved Infrastructure Company which agreed to pay Rs 55.55 crore. It will now sign the MoU with the firm.
Earlier, NMC had roped in MahaMetro for construction of the mall on 20 December 2018. MahaMetro was supposed to complete the project in 18 months but it could complete the construction only up to the plinth level.
The project department has also proposed stage-wise payments to be made by the firm to the civic body. As per the proposal, within 60 days of appointment, the firm will have to pay Rs two crore in the first installment and Rs three crore in six months.
Apart from this, 14 more proposals will be tabled before the standing panel meeting to be presided over by its Chairman Prakash Bhoyar.
The other proposed works include laying of sewer line worth Rs 49.88 lakh in Khalasi Line in Gaddigodam, construction of retaining wall of a nullah in Shivaji Nagar under Gandhibagh zone for which it has proposed to spend Rs 88.20 lakh.