Illustrative image – not actual.Power Finance Corporation (PFC) has reportedly agreed to be the lead lender for the Rs.4,400 crore 1015 MW Nagarjuna Power Project in Karnataka.
This decision comes in the wake of state government agreeing to the default escrow mechanism along with guarantee to make the project bankable. The payment security mechanism would be on the lines of Andhra Pradesh model involving planning and monitoring of the reform process, assessing the increase in annual revenues of the utility consequent to the reform process, charging the receivables till the implementation of the project with provision of escrow before the commercial operation date.
The project will
have a debt-equity ratio of 70:30 with export credit agencies and financial
institutions contributing to the debt component. The debt component will consist
of foreign debt of Rs.2,200 crore and rupee debt of Rs.800 crore along with a
payment guarantee of 50 per cent of foreign debt.