The Nagarjuna group has sought an extension of the techno economic clearance (TEC) beyond June 2001 from the Central Electricity Authority, for its 1,015 MW Mangalore power project, following the state government's delay in clearing the same.

 

The company stated that it had submitted the project for government approval of the state support agreement and power purchase agreement about 10 months ago. However, the project was taken up before the Cabinet.

 

The cost of the project is estimated at Rs.5,000 crore. Alstom of France would be the EPC contractor for the project. The promoters have also finalised the fuel supply for the project from Australia.