Illustrative image – not actual.The project entailing an investment of Rs 170.70 crore involves lifting of 0.597 TMC water from Krishna river to provide irrigation facility to 3,200 ha of command area and benefiting 14 villages.
The project has been facing delays due to land issues. In October 2018 the State level Environment Impact Assessment Authority (SEIAA) accorded environmental clearance (EC) for the project.
As per the latest information collated by Projects Today, work on head works is still underway with completion rescheduled for December 2019. The project is expected to be completed by 30 November 2020.