Mysore-Kozhikode power line project faces green hurdleIllustrative image – not actual.

The Mysore-Kozhikode power line project proposed by Power Grid Corporation of India (PGCIL), is facing a green hurdle in Kodagu district of Karnataka.

 

The proposed project involves laying of a 400 kV, 210 km long, high tension line between Mysore and Kozhikode. The line will pass through 92 km in Kerala.

 

Work has been stalled as members of Kaveri Sene, Coorg Wildlife Society, and Kaveri Bachao Andolan are opposing the project, citing that it will have its impact on the bio-diversity and environment of the region, and have suggested the PGCIL look for an alternative route.

 

Earlier, in 2009, three alternative routes were suggested by the protesters, which were rejected. The first route was to upgrade the 220 kV line that provided connectivity between Karnataka and Kerala. The upgraded line was falling under Bandipura National Park and as per the Forest Conservation Act 1980, no development work can be taken up inside the National Park, and this alternative was rejected.

 

Route two suggested laying of electric wire on D-line of Nagarahole National Park, but this route was also rejected as the width of the D-line was only 15 mtr and the width required for laying high-tension wire is 45 mtr. Thus, to get 30 mtr of plot, about 17,515 trees would have been felled if the route was approved.

 

The third route was rejected as it suggested laying of underground cable for 55 km and for laying the cables underground, a separate road would have to be constructed.

 

The present route decided that the high-tension line would pass through Hunsur, Piriyapattana-Devamacchi forest-Maldare-Hundi-Mayamudi-Bekkesodlur-Nalkeri-Kutta-Kerala.

 

In order to explore a possible alternative route for this project, the Karnataka government has set up a technical committee which will look into the matter. The committee has been directed to submit its report within 15 days.