Illustrative image – not actual.The Airports Authority of India's refusal of the Karnataka Government's plea for sharing the land acquisition cost, plans to develop the Mysore Airport at Mandakalli have been delayed further.
AAI had not accepted the request of the state government for cost sharing, because as per the MoU signed between them on 6 October 2005, any additional land required for expansion of the Mysore Airport is to be acquired by the state and transferred to the AAI, free of cost and free from all encumbrances.
In Phase I, AAI had taken up the development of Mysore Airport for ATR-72 type of aircraft operations. Accordingly, it has completed construction of the runway 09/27 of dimension 1,740 x 30 mtrs, apron and link taxiway with associated facilities in March 2008.
For the Phase II development, AAI has requested the state to provide additional 310 acre, including diversion of NH-212 for future expansion plans.