Illustrative image – not actual.The 2.14 million tpa greenfield cement project of Murli Agro Products attained financial closure in the first week of August 2006, company officials informed ProjectsToday. The Rs.578 crore project is coming up at Korpara in Chandrapur district of Maharashtra.
Elaborating on the project status, company officials stated that land acquisition was currently underway. The company is hopeful of completing the same in the next two months. Work on the project is likely to start in October 2006 with completion scheduled for April 2008.
The 2.14 million tpa cement plant represents Phase I of a two-phase project costing Rs.900 crore. In Phase II, another cement unit, whose capacity is yet undecided would be set up. The second phase will also involve a 30 MW coal-based power plant for which coal linkages were being sought from the Union government.