Illustrative image – not actual.Coastal Gujarat Power, an SPV formed by Tata Power Co for the 4,000 MW Mundra Ultra mega Power Project in Kachchh district is likely to achieve financial closure by March 2008.
The company will be funding the project through a debt-equity ratio of 80:20, with the option of overseas and domestic debt being considered for shoring up funds for the project, which will entail total investments of up to Rs.20,000 crore. Tata Power had earlier appointed SBI Capital Market as its advisor for raising the funds.
While the terms of the bid stipulate commissioning of units starting from the first half of 2012-13, the company hopes to commission the first unit ahead of schedule. The construction work is likely to commence by 2008 and the first 800 MW super-critical technology-based unit is expected to go on stream by July 2011.
Also See:
TPC signs EPC contract with Toshiba Corporation for steam generators (10-Aug-07)
Related Links:
Project profile