Illustrative image – not actual.The Mundra UMPP of Tata Power is awaiting clearance from the Central Electricity Regulatory Commission (CERC).
Coastal Gujarat Power, a SPV formed to ensure the initial clearances for the 4000 MW project had filed a petition for adoption of tariff way back in February 2007 with the CERC. The delay in clearance of the tariff plan has further delayed the process of financial closure. The initial delays in clearances of the project has put question mark on the completion of the project in the Eleventh Plan period.