Illustrative image – not actual.The MMRDA is likely to throw open the first line of high speed monorail in Mumbai by December 2012.
The first line will connect Chembur in the eastern suburbs to Wadala in Central Mumbai with a 8.26-km elevated track. Construction work on the elevated lines, stations and monorail depot, is expected to be completed by October 2012 and safety audit will be carried out by the consultants thereafter. The MMRDA has roped in SMRT, Singapore, as the safety certification agency. One train of monorail with four compartments will have capacity for 562 passengers, while one with six cars will be able to accommodate 852 passengers.
Further, work on the second line (11.28 km) is expected to be completed by December 2013. This line will connect Jacob Circle in South Mumbai to Wadala. So far, 45 per cent of the work has been completed on this line.