Mumbai Urban Transport Project: A ProfileIllustrative image – not actual.
What is MUTP II

Mumbai Urban Transport Project (II): A Profile

(Updated as of 31 March 2001)

 

Introduction

 

The Mumbai Urban Transport Project (II) is a Rs.7,700 crore multi-modal project aimed at streamlining and decongesting the existing transport system in the metropolitan city of Mumbai through improved rail and road services. The project, currently under implementation, is being funded largely through financial assistance from the World Bank (See Role of World Bank in MUTP II). The project has a gestation period of around seven years. MUTP-II, also known simply as MUTP, is being implemented by the Mumbai Metropolitan Region Development Authority (MMRDA) in concert with other entities such as Mumbai Rail Vikas Corporation (MRVC), Maharashtra State Road Development Corporation (MSRDC), Brihanmumbai Electricity Supply & Transport (BEST), Brihanmumbai Municipal Corporation (BMC) and the Mumbai Traffic Police Department, among others.

 

Background

 

The genesis of MUTP II can be traced to the formation of the Mumbai Metropolitan Region Development Authority (MMRDA) in January 1975. This entity was formed with a view to developing the Mumbai Metropolitan Region comprising the capital city of Mumbai and the fast-developing hinterland.

 

MMRDA embarked upon its first project, Mumbai Urban Transport Project (MUTP) – I, in 1976. This project, then costing Rs.39 crore, was completed in 1983. The project’s focus area was on improving the road transport facilities. The main achievements of MUTP – I have been:

 

  • Construction of five flyovers near high-traffic areas in Mumbai
  • Construction of pedestrian bridges and underpasses at important junctions
  • Procurement of over 700 buses for BEST
  • Installation of microprocessor-based traffic signals at 77 major road junctions

 

In 1988, the State government of Maharashtra approached the World Bank for financial assistance for an ambitious project to improve the transport facilities – mainly road transport and traffic control systems – in Mumbai and suburban areas. Thus was conceived the Mumbai Urban Transport Project (MUTP) – II.

 

The World Bank was in broad agreement with the Government of Maharashtra, but insisted that the project assume the form of a combined railway and roadway project; the insistence stemming from the growing importance of railway transport in Mumbai and suburban areas. (See Railway Traffic in Mumbai)

 

Soliciting participation from the Indian Railways did not come about easily. It took about five years (till around 1993) for the Indian Railways to even commit tentative participation. This commitment remained largely on paper till 1997; the Railways always citing paucity of funds as a deterrent. It was only in 1998 that the Indian Railways entered into an in-principle agreement with the Government of Maharashtra to participate in the MUTP II on a 50:50 basis. 

 

In July 1999, the Mumbai Rail Vikas Corporation (MRVC) was incorporated as a 51:49 joint venture between the Indian Railways and the Government of Maharashtra, with an equity capital of Rs.25 crore. (See box MRVC: Origin & Objectives)

 

Meanwhile, in an independent development, Maharashtra State Road Development Corporation (MSRDC) was incorporated as a limited company, fully owned by the government of Maharashtra, on 2 August 1996.The main objective of MSRDC is to accelerate the development of road transport facilities in the State.

 

With the formation of MSRDC and MRVC, the nature of MUTP II changed considerably from that of its forerunner MUTP I. Unlike its predecessor, MUTP II is not solely a responsibility of MMRDA but involves a wider participation of government agencies. MUTP II is also much larger in scope entailing railway projects and the concomitant rehabilitation and resettlement of project-affected persons.

 

Project Scope

 

The MUTP II project can be broadly divided into three parts -- Suburban Railway Component, Road and Traffic Management Component, and Rehabilitation and Resettlement of project-affected persons (PAPs). The entire project has been divided into two phases of which the first phase is under implementation. Even here, it is the rehabilitation and restoration of project-affected persons that is uppermost in the implementation schedule. The scope of the second phase has not been clearly defined since this would be considered only after Phase I is successfully implemented. Moreover, as of now, there exists no firm World Bank commitment for Phase II of the project. Phase I is targeted for completion by 2006.

 

Project Cost

 

The cost of the MUTP II is an estimated Rs.7,700 crore, at current prices. Table 1 gives the approximate break-up of the total cost. (Please note that that the cost of Phase II of the project is indicative).

 

Table 1: Project Cost of MUTP II

Component

(Rs.crore)

 

Phase I

Phase II

Total

Suburban Railway

3,108

2,545

5,653

Road & Traffic Management

753

947

1,700

Rehabilitation of PAPs*

320

320

*Only Railway Component has been considered

 

 

 

Project Details

 

A. Road & Traffic Component

 

Projects falling under the road and traffic component of the MUTP II are being implemented by a variety of agencies such as MSRDC, BEST and BMC. This component has a total cost of around Rs.1,700 crore.

 

Phase I of this component is currently underway at an estimated outlay of Rs.753 crore. The main projects encompassed by this phase are given in Table 2.

 

Table 2: Road & Traffic Component of MUTP II

(Phase I only)*

Project Segment

Cost

 

(Rs.crore)

Jogeshwari-Vikhroli Link Road

102

Santacruz-Chembur Link Road

154

ROB at Jogeshwari (South)

65

ROB at Jogeshwari (North)

44

ROB at Vikhroli

28

Buses

120

Pedestrian Subways and Bridges

30

Area Traffic Control

65

Station Area Traffic Improvement

30

Other Traffic Management Schemes

35

Dadar-Mahim One-Way System

5

Air Quality Monitoring System

25

Technical Assistance, Training, etc.

50

Total

753

*Complete details of Phase II are not available

 

Development of roads and bridges is the main aspect of this component, taking up Rs.423 crore or 56 per cent of the total cost.

 

Another Rs.120 crore (or 16 per cent of the total cost) has been earmarked for procurement of buses. This project segment falls under the purview of the BEST.

 

The remaining 28 per cent of the project cost would be spent mainly towards traffic control systems.

 

The road and traffic component also entails the rehabilitation and resettlement of over 4,500 families, which would be affected by the first five project segments given in Table 2. The cost of rehabilitation has been included in the respective project segment cost.

 

B. Railway Component

 

Railways-related projects form the backbone of the MUTP II and are being implemented by Mumbai Rail Vikas Corporation. Out of the total outlay of Phase I, a sum of Rs.3,108 crore (or nearly 75 per cent) has been earmarked for this component. Table 3 gives the fourteen project segments that constitute the Railway component of MUTP II.

 

Optimization of the Western and Central Railways and the Harbour Line is the most significant facet of the Railway component of MUTP II, accounting for 35 per cent of the total cost. Projects for the optimization of the Western and Central Railway are described below.

 

Western Railway

 

Scope: This project would begin with the removal of all level crossings between Borivili and Virar. A semi-terminus at Goregaon and a new railway station at Oshiwara has also been envisaged. Overall improvement in the Western Railway system has been targeted through lengthening of platforms, installation of new signaling equipment, increase in power supply and procurement of additional rakes.

 

Benefit: The project will permit the maximum feasible 18 trains per hour on the local line between Churchgate and Borivili. Similar improvement would be seen in the case of trains running on the through lines between Churchgate and Virar. There would be an expected 35 per cent increase in the train kilometers (i.e. number of trains multiplied by distance travelled), due to installation of new rakes.

 

Status: This project is under execution.

 

Table 3: Railway Component of MUTP II

(Phase I and II)

(Rs.crore)

Project Segment

Project Cost*

World Bank

 

Phase I

Phase II

Total

Assistance

5th Line between Santacruz & Borivili

158

---

158

49

Extra pair of lines between Kurla & Thane

399

---

399

172

Borivili-Bhayandar (Additional Pair of Lines)

229

---

229

81

Bhayandar-Virar (Additional Pair of Lines)

348

---

348

78

Optimisation of Western Railway**

365

463

828

556

Optimisation of Central Railway**

444

415

859

181

Optimisation of Harbour Line

259

32

291

150

5th Line (Kurla - Dadar - CSTM)

---

229

229

36

6th Line between Borivili & Santacruz

---

210

210

45

East-West Bandra Kurla Link

---

975

975

902

DC - AC Conversion

400

201

601

313

EMU Manufacture

450

---

450

375

Track Machines

12

20

32

32

Technical Assistance

44

---

44

44

Total

3,108

2,545

5,653

3,014

*Project cost is inclusive of World Bank assistance

 

 

 

**Includes procurement of 12-Coach Rakes

 

 

 

 

Central Railway

 

Scope: The project scope entails the reconditioning of tracks on the Central Railway line. The two yards at CST and Kalyan would also be re-modelled. Besides, new signaling equipment would be installed in the local corridor and the level crossing at Vikhroli would be removed. Power supply to the Central Railway line would also be augmented.

 

Benefit: The optimization would permit 16 trains (with nine rakes) per hour on the local line and 12 trains (with 12 rakes) per hour on the through line in the CST-Kalyan section.

 

Status: The project is under implementation.

 

 

 


Out of the total 14 projects of the Railway component of MUTP II, eight projects were under implementation, as of March 2001. The largest railway line project envisaged in the Railway component is the East-West Bandra-Kurla Link project. The project, to be taken up in Phase II of MUTP II, would cost around Rs.975 crore. The World Bank would be funding this project to the extent of Rs.902 crore, or 93 per cent.

 

Besides offering a direct link between the Central and Western Railway lines, the project would also provide additional facilities. Presently, a journey from Bandra to Kurla entails change of route at Dadar. The new link would obviate this change of route and would help alleviate the present congestion at Dadar. This project would also provide a direct rail link to the fast-developing Bandra-Kurla complex. Besides, a direct rail link between Andheri and Panvel has also been envisaged.

 

Rehabilitation & Resettlement of Project Affected People

 

As mentioned earlier, the rehabilitation and resettlement of project affected people (PAPs) forms an integral part of the MUTP II.

 

Table 4: Rehabilitation under MUTP II

(As on 23 January 2001)

Project

Number of PAPs Rehabilitated

 

Permanent

Transit

Total

 

Tenements

Tenements

 

Optimisation of Harbour Line

1,521

2,319

3,840

Kurla-Thane New Lines

254

935

1,189

Santacruz-Borivli New Line

103

17

120

Total

1,878

3,271

5,149

 

This aspect assumes significance not due to its project cost but due to the fact that World Bank assistance is governed by how ably this social project is handled.

 

Of the two major components of the MUTP II, it is the Railway component that entails most of the rehabilitation and resettlement of persons. This is particularly true of projects that envisage optimizing of the Central, Harbour and Western Railway Lines. The numberof families that would be affected by the MUTP II is estimated at 19,128. Of this 4,649 families would be affected by the road and traffic component, while a large chunk of 14,479 families would face dislocation by Railways-related projects.

 

The work of clearing hutments from areas adjoining railway tracks commenced even before the formation of MRVC. At the time of inaugurating the MRVC (July 1999) the Union Minister for Railways handed over 800 transit tenements to PAPs.

 

During January 2001, MMRDA handed over 1,441 permanent tenements to an equal number of project affected families. At the same time, work for constructing 3,600 transit tenements was initiated. It was estimated that by the end of March 2001, rehabilitation of an additional 5,000 PAPs would be completed.

 

MRVC: Origin & Objectives

 

Maharashtra Rail Vikas Corporation (MRVC) is the culmination of the formal agreement between the Indian Railways (IR) and the Government of Mahrashtra (GoM) to implement the railway component of the MUTP II. MRVC can be construed as a by-product of World Bank’s insistence. The inclusion of railway projects under the proposed MUTP and the formation of a corporate entity to implement the same were the prime pre-conditions for receiving World Bank assistance when the Government of Maharashtra first approached the World Bank in 1988.

 

MRVC was incorporated on 12 July 1999, after much deliberation between the GoM and the IR. It was often feared that MRVC would never see the light of the day given the inertia of the IR in committing to a joint venture. Had the IR responded to the GoM’s proposal when the World Bank first laid out its pre-condition, MRVC would have been formed by around 1990. Even after having agreed to a joint venture in 1993, it took six more years for MRVC to take form. With the result, MUTP II has suffered inestimable cost overruns during this period of hibernation from 1993 to 1999.

 

MRVC is a 51:49 joint venture between the IR and GoM. It has an equity capital of Rs.25 crore. MRVC was inaugurated on 29 April 2000 at the hands of Ms Mamta Banerjee, the then Union Minster for Railways.

 

MRVC is much more than a special purpose vehicle to implement the railway component of MUTP II, it has, among others, a big task of ultimately unifying the operations of Western Railway and Central Railway -- the two prime agencies currently managing the suburban railway network in Mumbai.

 

The main objectives of the MRVC are:

·          Developing and co-ordinating plans for rail projects included under the MUTP II and other such planned investments for Mumbai’s rail services.

·          Ensuring improvement of track drainage and removing encroachments from the right of way of the Railways.

·          Undertaking rehabilitation and resettlement of persons affected by the MUTP II and subsequent projects.

·          Undertaking commercial development of Railway land and airspace.

 

It may be mentioned that the revenue earned through commercial use of railway land and airspace would part-finance the Railway component of MUTP II and subsequent projects. As per the MoU between the IR and GoM, the revenue earned by the exploitation of Railway land and airspace would be shared equally between the IR, GoM and MRVC. The GoM would spend its share of revenue on development of railway projects in Maharashtra, whereas the IR would be free to deploy its revenue share as per its discretion.

 

Role of World Bank in MUTP II

 

The role of World Bank as a funding agency is critical to MUTP II. World Bank, subject to conditions, has agreed to finance up to 70 per cent of the total cost of the project. The fructification of MUTP II therefore hinges on the fulfilling of World Bank conditions.

 

The first pre-condition was imposed by the World Bank when the GoM first approached the agency with the ambitious MUTP, in 1988. The World Bank insisted that the project be blended with a significant portion of railway projects. It further demanded that a separate entity be set up for overseeing these projects. It was this pre-requisite that ultimately saw the birth of MVRC. World Bank also maintained that funding would be contingent on the removal of encroachments lying in the right of way of the Railways, and the rehabilitation and resettlement of persons so affected. This rehabilitation is expected to cost Rs.320 crore, 90 per cent of which would be funded by World Bank. Resettlement of PAPs is reportedly progressing satisfactorily, boding well for the future of MUTP II.

 

During his visit to India in November 2000, World Bank President, Mr James Wolfensohn, sanctioned Rs.2,000 crore towards the MUTP II. The disbursement is expected to be made by May 2001. Assistance is expected to materialize in tranches, albeit subject to a continual adhering to WB conditions.

 

Railway traffic in Mumbai

 

Mumbai Rail Vikas Corporation (MVRC) has estimated that the Mumbai suburban railway has the highest density amongst similar large-volume suburban services in the world. It is learnt that the Mumbai suburban railway, with a total route length of 302 km, carries around 6.1 million passengers per day. This translates to a passenger density of over 20,000 persons per km per day. The table alongside shows comparable density of some other important cities in the world

 

Passenger Density in Major Suburban Railways

City

Passengers

Route

Passenger

 

per day

Length

Density

 

(million)

(kms)

('000/km/day)

Mumbai

6.10

302

20.20

Tokyo

18.90

1,272

14.86

Seoul

2.20

171

12.87

Buenos Aires

2.10

819

2.56

Rio de Janeiro

0.17

264

0.64

Values estimated by MRVC

 

 

 