Illustrative image – not actual.Nine percent work has been completed on the Mumbai Trans Harbour Link (MTHL) corridor. The project aims to ease travel time between Mumbai and Navi Mumbai. The corridor, which commenced work in March 2018, is being constructed in three phases.
On Phase-I, which involves construction of 10.38 km bridge, 12.28 percent of the work has been completed. On Phase-II which involves construction of 7.807 km section, 5.37 percent work has been completed; On Phase III, 3.613 km bridge viaduct, 5.4 percent progress has been recorded.
A total of 751 bore holes in marine and land areas have been completed for geo-technical investigation and 11 percent of the 2.9 km long temporary bridge has also been constructed. The project is expected to be completed by September 2022.