Illustrative image – not actual.Around 2,000 redevelopment housing projects in Mumbai which are estimated to cost between Rs 35,000-40,000 crore, have been stuck with Municipal Corporation of Greater Mumbai (MCGM).
Most of the redevelopment projects belong to the South Mumbai area. Apart from 2,000 real estate projects, more than 700 projects are stuck under Development Control Rules 33 (7) alone, while many projects of Slum Rehabilitation Authority (SRA) and Maharashtra Housing and Development Authority (MHADA) are also facing the heat.
The major reason behind the delay is the new directive passed by the Supreme Court, which instructs the builders to keep six mtr space between two buildings while developing any property. This leaves very little scope for redevelopment as many old buildings have been constructed very close to each other, and leaving six mtr space is turning out to be a loss-making venture for builders.
Also, cost of construction has gone up and builders have to shell out extra for FSI, which further escalates the price. Besides, in many redevelopment projects, homes have to be reserved for the economically weaker sections.
Due to the six mtr decree, redevelopment of about 16,000 buildings in South Mumbai area alone has been affected.